We are renovating our wellness building with sauna area
Dear guests,
for some time now, we have been busy planning how we will rebuild our wellness building with sauna area, café and sanitary facilities (below the building). It was very important to us that the access to the indoor pool is unrestricted during this time. The remodelling will take place in several construction phases.
We will start in September 2024 with the renovation of the sanitary facilities under the wellness building, which will be completed around Christmas 2024.
During the operating holiday in spring 2025, the café at the indoor pool, the changing rooms and the sauna area will be demolished. In the following months, we will work on the interior construction of these areas.
In the period from 19th May 2025 to mid-December 2025, the café, the changing rooms, the children's showers, the sauna area and the fitness room (as it will probably not be possible to pass through) will therefore not be in operation!
The use of the indoor pool (with all pools, water slide and relaxation room) remains guaranteed during the entire renovation! We will also set up a temporary solution for the changing rooms.
The toilets and showers will remain accessible until 9th November 2025 and will then be renovated.
If everything goes according to plan, we will be able to open the new wellness building on Christmas 2025. The following years, a new slide world will be added to the indoor pool – so stay tuned! :-)
We ask for your understanding that there may be temporary noise disturbance during the renovation work. We will do our best to offer our guests a relaxed stay and try to limit the noise pollution as much as possible, especially during the holiday periods.
The remodelling will be another challenge, but we are already looking forward to the final result!
Your Aufenfeld team
Construction timetable
Part I - Sanitary facilities
09.09.2024 - Start of construction (demolition of the sanitary facilities in the indoor pool basement, new interior fittings)
20.12.2024 - Completion of sanitary facilities
Part II - Renovation of café, changing rooms, sauna area
28.04.2025 - Demolition work on ground floor and 1st floor (café, changing rooms and sauna)
19.05.2025 - Start of interior work on café, changing rooms and sauna
10.11.2025 - Start of demolition and redesign of the showers and toilets in the indoor pool
Mid-Dec. 2025 - Completion of all areas
Part III - Water slides
2026/2027 - Construction of the new slide world